Address: Streatham, London
Client: London Borough of Lambeth
Project Value: £220,000
Project Started: 21/07/2014
Contract Period: 61 weeks
St Leonards Primary School is located in Streatham, London. In advance of the school’s expansion project, we have been contracted to commence enabling works and provide temporary classroom accommodation for the pupils.
Demolition works are to be carried out during the school summer holidays. However Heras fencing will be installed at all times during the demolition works to ensure the area is secure and safe. The temporary classroom module must be ready for occupation at the beginning of the school year in September.
Summary of Works
Address: SCL Construction Ltd
Unit F 61 Albert Road North
Reigate
RH2 9EL
Tel: 01737 420126
Email: info@sclconstruction.net